Reconstruction of the OHL 400 kV Mukachevo-Kapusany section from SS 400 kV Mukachevo to the state border in Zakarpattia region

Submited by Ukraine

Report:
Year registered: 2024
Type:
Energy
Status:Registered
3SI countries proposing the project:

Ukraine

Participating 3SI countries:

Slovakia

Partner countries:

* not part of the 3Seas Initiative
Main objectives:

Reconstruction and upgrading of existing OHL between Slovakia and Ukraine and related substations will increase the transmission capacity between the Slovak and Ukrainian power systems. The project will prepare the way for integration of power systems of Ukraine and Moldova into the European electricity market.

Implementation of the project will improve system stability in the given region. Eliminating the existing restrictions on power flows between the Slovak and Ukrainian power systems on the one hand, and the Hungarian and Romanian and Ukrainian power systems on the other will affect the pricing and conditions of the European electricity market.

Short description:

This project has already been identified as a Project of Common Interest (PMI) for the development of European transmission infrastructure. The project was also supported by the Slovak system operator SEPS.

It is planned to reconstruct the 400 kV outdoor switchgear at the Mukacheve substation to replace the physically and morally worn-out main equipment and to enable the connection of an additional 400 kV OHL in the direction of the Velke Kapusany 400 kV substation.

The project envisages increasing the capacity of the Ukraine-Slovakia interconnector to 1000 MW

Calendar of implementation:
  • 2018-2024
    Construction

    Phase I

  • 2028
    Construction

    Phase II

Budget:

Estimated cost: EUR 10 mln (Ukraine), EUR 6-12 mln (Slovakia)

24M0%
secured
Financing sources:
National funding