Upgrade of the Rijeka Port infrastructure - Bakar bulk cargo terminal (POR2CORE-BCTB)

Bakar bulk cargo terminal (POR2CORE-BCTB)

Report:
Year registered: 2018
Type:
Transport
Status:Completed
3SI countries proposing the project:

Croatia

Participating 3SI countries:

Partner countries:

* not part of the 3Seas Initiative
Main objectives:

The Bakar Basin is a part of the Port of Rijeka. Its existing railway infrastructure is aging, severely damaged and unsafe, hindering the efficiency of daily port operations.

  • The project's main objective is the reconstruction of the railway infrastructure connecting the Podbok terminal to the existing Bakar freight railway station. Specific objectives of the project are rehabilitation of damaged infrastructure, improved interoperability, faster port operations, increased safety and better quality of service.
Short description:

The project aims to improve efficiency of cargo handling at Podbok terminal and improve connectivity of Bakar basin (and consequently of the whole Rijeka port) with the TEN-T railway network. The project is developed in parallel with other railway infrastructure-upgrading project at the Port of Rijeka co-financed by CEF, which contribute to the improvement of port operations as well as the facilitation of the transport of goods. The project is focused on reconstruction activities that include removal of the existing infrastructure, reconstruction of installations, drainage and waste water system, reconstruction of the pavement surface and reconstruction of railway tracks.

Calendar of implementation:
  • 2017-2021
    Construction

    Implementation is extended to year 2021. Construction of work has started.

Budget:
  • Project budget – 6.094.664

  • EURCo-financing by CEF – 5.180.464

  • EUR Port of Rijeka Authority – 0.03 mio

  • EUR Luka Rijeka j.s.c. – 0.9 mio EUR

6.095M100%
secured
Financing sources:
CEF