Zlobin-Bosiljevo Pipeline
Report:
Year registered: 2023
Type:
Energy
Status:Registered
3SI countries proposing the project:
Croatia
Participating 3SI countries:
Croatia
Partner countries:* not part of the 3Seas Initiative
Main objectives:
The construction of the new gas pipeline will set the main preconditions for further development of the gas transmission system and increase of the existing transmission capacities towards Hungary and Slovenia
Short description:
The Croatian government on 18 August 2022 decided on investing €155 million in the construction of the Zlobin-Bosiljevo gas pipeline. Gas pipeline is of nominal diameter 800 mm, with maximum operating pressure 100 bar, and length of 58 km. The construction of the new gas pipeline will set the main preconditions for further development of the gas transmission system and increase of the existing transmission capacities towards Hungary and Slovenia
Calendar of implementation:
- 2022-2023Planning
- 2023-2024Design
- 2025Construction
Budget:
€155M0%
secured
secured
Financing sources:
CEF
National funding
Whether innovative, safe and sustainable new technologies are to be used